Connect with us

Energy & Critical Metals

Revitalizing a 99-year-old hydropower turbine

When a critical hydropower turbine failed at a hydropower plant in West Java, Sulzer was able to get the 5MW unit back online in less than half the time…

Share this article:

Published

on

This article was originally published by Power Engineering International

The Indonesian government is heavily investing in the country’s hydropower capacity to support growth, lower emissions and reduce dependency on fossil fuels.

As well as building new installations, keeping existing facilities operational is equally important for this strategy.

When a critical hydropower turbine failed at a hydropower plant in West Java, Sulzer Indonesia was able to get the 5MW unit back online in less than half the time needed for a new turbine to be manufactured and installed.

Nearly a century of reliability

The hydropower plant was originally built in the 1920’s and is owned by one of Indonesia’s oldest hydropower independent power producers (IPP).

It consists of three separate installations, supplying electricity to the local community and the wider grid.

With the operator having no local back-up system, any unforeseen downtime at any of the facilities results in an electricity shortage.

Have you read?
ANDRITZ wins contract to modernize Jaguara hydropower plant in Brazil
EnergyAustralia starts environmental studies for Lake Lyell Pumped Hydro

After almost a century of reliable operation, the support bolts installed on one of the turbine shafts finally failed. This caused the turbine to run in an uncontrolled manner. The turbine shaft split completely in two, smashing the casing to pieces while damaging the turbine tips, runner casings and the bearing pedestal.

Unsurprisingly, this resulted in complete turbine failure.

Reacting to an energy shortage

Requiring an urgent repair to overcome the resulting energy shortage, the IPP approached several independent service providers (ISPs). However, no suitable proposal was forthcoming. This was not ideal, as the electricity shortfall had to be covered from other sources, placing increased stress on the energy infrastructure.

The operator approached Sulzer Indonesia to leverage Sulzer’s network of localized service centers ready to deliver complex repairs and upgrades.

Sulzer experts inspected the damaged equipment thoroughly, checking dimensions and scanning it to identify the best approach. The company recommended a cost-effective restoration project, with all work to be delivered within five months. This was less than half the expected 12-month lead time for sourcing all new equipment. The customer agreed with Sulzer’s proposed approach, enabling work to begin.

Welding expertise

The project started with the more complex repair of the broken shaft.

Specialist welding processes were used to clad the blade tips with corrosion resistant material, ensuring an optimum repair. Image credit: Sulzer

In terms of direct replacement, the only option to source a shaft of the correct diameter was to order from overseas. This was unacceptable due to the long lead-time, so instead, Sulzer Indonesia sourced a smaller diameter shaft locally and built it up on the coupling area to the correct size.

This process has been used by Sulzer Indonesia since 2002 as it enables rotors to be weld repaired instead of being scrapped. The technology has been adopted from Sulzer’s Houston Service Center.

In this case, submerged arc welding (SAW) was used to apply an upgraded, high-strength low-alloy steel weld material, building up the diameter of the shaft. Once completed, the shaft was precision machined to the final dimensions and comprehensively tested.

A turnkey approach to projects

The damaged turbine tips also needed to be repaired.

Sulzer used laser scans in conjunction with reverse engineering techniques to ascertain the as-new dimensions. Then, specialist welding processes were used to clad the blade tips with corrosion-resistant material, ensuring an optimum repair.

The new shaft and repaired turbine were then reassembled. A replacement sleeve was also manufactured and fitted. Inspections and non-destructive testing (NDT) were conducted, along with low-speed balancing and demagnetization of the complete rotor.

Another challenging aspect of the repair was the smashed casing.

Machining of the repaired turbine tips. Image credit: Sulzer

Taking the scans and dimensions collected during the inspection, Sulzer reverse engineered the elbow casing. This allowed the team to use metal stitching to connect pieces of the smashed casing together. It was then machined before NDT and a complete hydrotest. The damaged runner casings and bearing pedestals also underwent repairs.

Bringing power to the community

With work complete, the rotor and casing were delivered back to the customer within the agreed project deadline.

All in all, the project was delivered in less than 50% of the expected OEM lead time for new components. As a result, the turbine could be quickly returned to operation, alleviating the local energy shortage and resuming supply of renewable electricity to the wider grid.

Delivering the project relied on Sulzer’s experience working with legacy equipment from any brand, ensuring familiarity with the application and technical expertise required to repair even legacy equipment which is almost a century old.

The incorporation of material upgrades into the design of the turbine delivered a long-lasting solution that will maximize power generation equipment uptime.

The turbine is now expected to operate reliably for at least another 30 years, ensuring that it will remain a dependable component of local energy infrastructure.

The post Revitalizing a 99-year-old hydropower turbine appeared first on Power Engineering International.


Share this article:

Uranium Exploration Company Announces Additional Staking in the Athabasca Basin

Source: Streetwise Reports 12/22/2023

Skyharbour Resources Ltd. announced an update from its Canada-based Falcon Project along with additional…

Share this article:

Published

on

By

Continue Reading
Energy & Critical Metals

Tesla Launches New Mega Factory Project In Shanghai, Designed To Manufacture 10,000 Megapacks Per Year

Tesla Launches New Mega Factory Project In Shanghai, Designed To Manufacture 10,000 Megapacks Per Year

Tesla has launched a new mega factory…

Share this article:

Published

on

Continue Reading
Energy & Critical Metals

Giving thanks and taking stock after “a remarkable year”

An end-of-year thank you to our readers, industry colleagues and advertisers before Electric Autonomy breaks from publishing until Jan. 2
The post Giving…

Share this article:

Published

on

Continue Reading

Trending